🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J4061, Lenawee County

Solar project J4061, Lenawee County is a 150 MW solar request in interconnection study in the MISO interconnection queue, in Lenawee County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4061
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
KNOWLES - MOORE ROAD 138.0kV
Location
Lenawee County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
7 August 2025
Proposed online date
November 2028

Location

Marker shows the centre of Lenawee County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Lenawee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem