United States › Grid › Interconnection queues › Michigan
SOLAR · MISOSolar project J1226, Lenawee County
Solar project J1226, Lenawee County is a 200 MW solar request under construction in the MISO interconnection queue, in Lenawee County, Michigan, connecting to METC.
Queue statusUnder construction
- PlanningQueued Apr 2019 (completed)
- ConsentedAug 2022 (completed)
- Construction (current stage)
- OperatingTarget Aug 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1226
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- Morocco 345 kV Substation
- Location
- Lenawee County, Michigan
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 27 April 2019
- Agreement signed
- 17 August 2022
- Proposed online date
- August 2024
Location
Marker shows the centre of Lenawee County; the queue data does not give exact sites.
Other requests in Lenawee County
- Solar project J875, Lenawee CountySolar · 150 MW · under construction
- Solar project J996, Lenawee CountySolar · 80.0 MW · under construction
- Solar project J1571, Lenawee CountySolar · 200 MW · agreement signed
- Onshore wind project J3313, Lenawee CountyOnshore wind · 263 MW · in study
- Battery storage project J4026, Lenawee CountyBattery storage · 250 MW · in study
- Onshore wind project J4120, Lenawee CountyOnshore wind · 200 MW · in study
- Solar project J4044, Lenawee CountySolar · 190 MW · in study
- Battery storage project J3651, Lenawee CountyBattery storage · 150 MW · in study
- Surplus; J875Other · 150 MW · in study
- Solar project J4061, Lenawee CountySolar · 150 MW · in study
- Onshore wind project J4126, Lenawee CountyOnshore wind · 112 MW · in study
- Other project L003, Lenawee CountyOther · -10.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem