Solar project J1226, Lenawee County

Solar project J1226, Lenawee County is a 200 MW solar request under construction in the MISO interconnection queue, in Lenawee County, Michigan, connecting to METC.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedAug 2022 (completed)
  3. Construction (current stage)
  4. OperatingTarget Aug 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1226
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Morocco 345 kV Substation
Location
Lenawee County, Michigan
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue status
Active
Entered queue
27 April 2019
Agreement signed
17 August 2022
Proposed online date
August 2024

Location

Marker shows the centre of Lenawee County; the queue data does not give exact sites.