🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

OTHER · MISO

Surplus; J1320

Surplus; J1320 is a 150 MW other request in interconnection study in the MISO interconnection queue, in Branch County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Aug 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1062
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
New Byers 138kV
Location
Branch County, Michigan
Technology
Other: 150 MW · Battery
Total requested
150 MW
Queue status
Active
Entered queue
15 August 2024
Proposed online date
October 2026

Location

Marker shows the centre of Branch County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Branch County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem