🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1916, Branch County

Solar project J1916, Branch County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Branch County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. ConsentedJul 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1916
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
NEWTON
Location
Branch County, Michigan
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
19 October 2023
Agreement signed
16 July 2025
Proposed online date
March 2026

Location

Marker shows the centre of Branch County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Branch County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem