United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Queue projects under construction in MISO (Midcontinent)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown12219.8 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

122 requests Β· page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J955, Sangamon County
Gas
1,165 MWUnder construction Sangamon, ILMISO Mar 2018target 2025
Gas project J732, Douglas County
Gas
562 MWUnder construction Douglas, WIMISO Jun 2017target 2023
Solar project J1060, St. Francis County
Solar
500 MWUnder construction St. Francis, ARMISO Mar 2018target 2023
Onshore wind project J844, Knox County
Onshore wind
300 MWUnder construction Knox, ILMISO Jun 2017target 2021
Solar project J976, Warren County
Solar
300 MWUnder construction Warren, MOMISO Mar 2018target 2024
Onshore wind project J1781, Iowa County
Onshore wind
300 MWUnder construction Iowa, WIMISO Jun 2020target 2027
Solar project J1730, Dunn County
Solar
300 MWUnder construction Dunn, WIMISO Mar 2022target 2027
Solar project J1421, East Feliciana Parish County
Solar
300 MWUnder construction East Feliciana Parish, LAMISO Apr 2019target 2024
Solar project J1410, Dane County
Solar
300 MWUnder construction Dane, WIMISO Apr 2019target 2025
Solar project J1058, Lake County
Solar
300 MWUnder construction Lake, INMISO Mar 2018target 2024
Solar project J813, Clay County
Solar
275 MWUnder construction Clay, ILMISO Jun 20172024
Onshore wind project J848, Christian County
Onshore wind
250 MWUnder construction Christian, ILMISO Jun 2017target 2021
Solar project J815, Christian County
Solar
250 MWUnder construction Christian, ILMISO Jun 2017target 2022
Solar project J877, Palo Alto County
Solar
250 MWUnder construction Palo Alto, IAMISO Jun 2017target 2023
Solar project J829, Sullivan County
Solar
250 MWUnder construction Sullivan, INMISO Jun 2017target 2022
Onshore wind project J1040, Mcintosh County
Onshore wind
250 MWUnder construction Mcintosh, NDMISO Mar 2018target 2023
Solar project J800, White County
Solar
250 MWUnder construction White, ILMISO Jun 20172024
Solar project J1067, Jasper County
Solar
240 MWUnder construction Jasper, INMISO Mar 20182024
Solar project J1034, Stoddard County
Solar
225 MWUnder construction Stoddard, MOMISO Mar 2018target 2024
Solar project J762, Meade County
Solar
200 MWUnder construction Meade, KYMISO Nov 2016target 2021
Solar project J992, Cass County
Solar
200 MWUnder construction Cass, INMISO Mar 2018target 2023
Solar project J1226, Lenawee County
Solar
200 MWUnder construction Lenawee, MIMISO Apr 2019target 2024
Onshore wind project J1069, Jasper County
Onshore wind
200 MWUnder construction Jasper, INMISO Mar 2018target 2023
Onshore wind project J1115, Macon County
Onshore wind
200 MWUnder construction Macon, ILMISO Mar 2018target 2024
Solar project J1460, Rock County
Solar
200 MWUnder construction Rock, WIMISO Apr 2019target 2025
Solar project J1107, Cape Girardeau County
Solar
200 MWUnder construction Cape Girardeau, MOMISO Mar 2018target 2023
Solar project J993, Boone County
Solar
200 MWUnder construction Boone, INMISO Mar 2018target 2023
Solar project J1007, Crittenden County
Solar
200 MWUnder construction Crittenden, ARMISO Mar 20182023
Solar project J934, Crittenden County
Solar
200 MWUnder construction Crittenden, ARMISO Jun 20172024
Solar project J1325, Rock County
Solar
200 MWUnder construction Rock, MNMISO Apr 2019target 2025
Onshore wind project J722, Codington County
Onshore wind
200 MWUnder construction Codington, SDMISO Jun 2017target 2023
Solar project J1559, Conway County
Solar
200 MWUnder construction Conway, ARMISO Jun 2020target 2026
Onshore wind project J984, Gratiot County
Onshore wind
200 MWUnder construction Gratiot, MIMISO Mar 20182023
Solar project J1076, St. James Parish County
Solar
200 MWUnder construction St. James Parish, LAMISO Mar 2018target 2022
Solar project J1424, Beauregard Parish County
Solar
200 MWUnder construction Beauregard Parish, LAMISO Apr 2019target 2024
Solar project J1299, Scott County
Solar
200 MWUnder construction Scott, MOMISO Apr 2019target 2025
Solar project J1663, Ottawa County
Solar
200 MWUnder construction Ottawa, MIMISO Dec 2021target 2025
Solar project J1255, Ionia County
Solar
200 MWUnder construction Ionia, MIMISO Apr 2019target 2025
Onshore wind project J866, Tunica County
Onshore wind
200 MWUnder construction Tunica, MSMISO Jun 20172024
Solar project J1087, Scott County
Solar
200 MWUnder construction Scott, MOMISO Mar 2018target 2023
Solar project J1458, Washington County
Solar
200 MWUnder construction Washington, MSMISO Apr 2019target 2024
Solar project J878, Kenosha County
Solar
200 MWUnder construction Kenosha, WIMISO Jun 20172024
Solar project J805, Shelby County
Solar
199 MWUnder construction Shelby, INMISO Jun 2017target 2022
Solar project J1063, Clinton County
Solar
195 MWUnder construction Clinton, INMISO Mar 20182024
Solar project J799, Washtenaw County
Solar
189 MWUnder construction Washtenaw, MIMISO Jun 2017target 2021
Solar project J919, Jackson County
Solar
180 MWUnder construction Jackson, ARMISO Jun 20172023
Onshore wind project J1437, Carroll County
Onshore wind
180 MWUnder construction Carroll, ARMISO Apr 2019target 2024
Solar project J1297, Shiawassee County
Solar
170 MWUnder construction Shiawassee, MIMISO Apr 2019target 2024
Solar project J1224, Washtenaw County
Solar
170 MWUnder construction Washtenaw, MIMISO Apr 2019target 2025
Solar project J1174, Worth County
Solar
165 MWUnder construction Worth, IAMISO Mar 2018target 2024
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)