United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J1559, Conway County
Solar project J1559, Conway County is a 200 MW solar request under construction in the MISO interconnection queue, in Conway County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusUnder construction
- PlanningQueued Jun 2020 (completed)
- Consented (completed)
- Construction (current stage)
- OperatingTarget Apr 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1559
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- Morrilton East Substation (161kV bus)
- Location
- Conway County, Arkansas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 18 June 2020
- Proposed online date
- April 2026
Location
Marker shows the centre of Conway County; the queue data does not give exact sites.
Other requests in Conway County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem