SOLAR · MISOSolar project J1063, Clinton County
Solar project J1063, Clinton County is a 195 MW solar request under construction in the MISO interconnection queue, in Clinton County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedMar 2022 (completed)
- Construction (current stage)
- OperatingMay 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1063
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- New London - Frankfort 230kV Line Tap
- Location
- Clinton County, Indiana
- Technology
- Solar: 195 MW
- Total requested
- 195 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 9 March 2022
- Proposed online date
- August 2022
- Came online
- May 2024
Location
Marker shows the centre of Clinton County; the queue data does not give exact sites.
Other requests in Clinton County
- Onshore wind project J2654, Clinton CountyOnshore wind · 180 MW · in study
- Onshore wind project V3-003, Clinton CountyOnshore wind · 500 MW · withdrawn
- Battery storage project J3354, Clinton CountyBattery storage · 250 MW · withdrawn
- Onshore wind project J312, Clinton CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project G935, Clinton CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project G999, Clinton CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project H001, Clinton CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J478, Clinton CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G836, Clinton CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G998, Clinton CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J1966, Clinton CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project H002, Clinton CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem