ONSHORE WIND Β· MISO

Onshore wind project J478, Clinton County

Onshore wind project J478, Clinton County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Clinton County, Indiana, connecting to Duke Energy Corporation.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J478
Grid region
MISO (Midcontinent)
Utility / transmission owner
Duke Energy Corporation
Connection point (POI)
Thorntown - New London - Kokomo 230kV Line
Location
Clinton County, Indiana
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
July 2018
Withdrawn
April 2019

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Clinton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem