United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· MISO

Onshore wind project H002, Clinton County

Onshore wind project H002, Clinton County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Clinton County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2009 (completed)
  2. Withdrawn / abandonedApr 2012 (project stopped here)
  3. ConsentedApr 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H002
Grid region
MISO (Midcontinent)
Connection point (POI)
Carmel - Kokomo 230 kV
Location
Clinton County, Indiana
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
24 July 2009
Agreement signed
18 April 2012
Proposed online date
December 2009
Withdrawn
April 2012

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Clinton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem