πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· PJM

Onshore wind project V3-003, Clinton County

Onshore wind project V3-003, Clinton County is a 500 MW onshore wind request withdrawn in the PJM interconnection queue, in Clinton County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2009 (completed)
  2. Withdrawn / abandonedFeb 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
V3-003
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Greentown-Jefferson 765kV
Location
Clinton County, Indiana
Technology
Wind: 500 MW
Total requested
500 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
5 August 2009
Proposed online date
December 2010
Withdrawn
February 2011

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Clinton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem