United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· MISO

Onshore wind project J1966, Clinton County

Onshore wind project J1966, Clinton County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Clinton County, Indiana, connecting to WABASH VALLEY POWER ASSOCIATION, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1966
Grid region
MISO (Midcontinent)
Utility / transmission owner
WABASH VALLEY POWER ASSOCIATION, INC.
Connection point (POI)
Cayuga - Frankfort 230.0kV
Location
Clinton County, Indiana
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 March 2022
Proposed online date
October 2025
Withdrawn
December 2025

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Clinton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem