United States › Grid › Interconnection queues › North Dakota
ONSHORE WIND · MISOOnshore wind project J1040, Mcintosh County
Onshore wind project J1040, Mcintosh County is a 250 MW onshore wind request under construction in the MISO interconnection queue, in Mcintosh County, North Dakota, connecting to MONTANA-DAKOTA UTILITIES CO..
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedFeb 2022 (completed)
- Construction (current stage)
- OperatingTarget May 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1040
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MONTANA-DAKOTA UTILITIES CO.
- Connection point (POI)
- Wishek Junction 230 kV Substation
- Location
- Mcintosh County, North Dakota
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 7 February 2022
- Proposed online date
- May 2023
Location
Marker shows the centre of Mcintosh County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Mcintosh County
- Other project G150, Mcintosh CountyOther · 12.0 MW · in study
- Coal project GI-0111, Mcintosh CountyCoal · 750 MW · withdrawn
- Onshore wind project GI-0114, Mcintosh CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GI-0115, Mcintosh CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2018-008, Mcintosh CountyOnshore wind · 252 MW · withdrawn
- Onshore wind project J209, Mcintosh CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project G988, Mcintosh CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G624, Mcintosh CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GI-0812, Mcintosh CountyOnshore wind · 150 MW · withdrawn
- Solar project J929, Mcintosh CountySolar · 25.0 MW · withdrawn
- Onshore wind project G283, Mcintosh CountyOnshore wind · 19.0 MW · withdrawn
- Onshore wind project G307, Mcintosh CountyOnshore wind · 19.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem