ONSHORE WIND Β· MISO

Onshore wind project G624, Mcintosh County

Onshore wind project G624, Mcintosh County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Mcintosh County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2006 (completed)
  2. Withdrawn / abandonedNov 2011 (project stopped here)
  3. ConsentedNov 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G624
Grid region
MISO (Midcontinent)
Connection point (POI)
Wishek Substation 115 kV
Location
Mcintosh County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
25 April 2006
Agreement signed
21 November 2011
Proposed online date
September 2007
Withdrawn
November 2011

Location

Marker shows the centre of Mcintosh County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mcintosh County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem