United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
ONSHORE WIND Β· MISOOnshore wind project G624, Mcintosh County
Onshore wind project G624, Mcintosh County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Mcintosh County, North Dakota.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2006 (completed)
- Withdrawn / abandonedNov 2011 (project stopped here)
- ConsentedNov 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G624
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Wishek Substation 115 kV
- Location
- Mcintosh County, North Dakota
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 25 April 2006
- Agreement signed
- 21 November 2011
- Proposed online date
- September 2007
- Withdrawn
- November 2011
Location
Marker shows the centre of Mcintosh County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Mcintosh County
- Onshore wind project J1040, Mcintosh CountyOnshore wind Β· 250 MW Β· under construction
- Other project G150, Mcintosh CountyOther Β· 12.0 MW Β· in study
- Coal project GI-0111, Mcintosh CountyCoal Β· 750 MW Β· withdrawn
- Onshore wind project GI-0114, Mcintosh CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GI-0115, Mcintosh CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2018-008, Mcintosh CountyOnshore wind Β· 252 MW Β· withdrawn
- Onshore wind project J209, Mcintosh CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project G988, Mcintosh CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-0812, Mcintosh CountyOnshore wind Β· 150 MW Β· withdrawn
- Solar project J929, Mcintosh CountySolar Β· 25.0 MW Β· withdrawn
- Onshore wind project G283, Mcintosh CountyOnshore wind Β· 19.0 MW Β· withdrawn
- Onshore wind project G307, Mcintosh CountyOnshore wind Β· 19.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem