πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· WEST

Onshore wind project GI-0115, Mcintosh County

Onshore wind project GI-0115, Mcintosh County is a 300 MW onshore wind request withdrawn in the West interconnection queue, in Mcintosh County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0115
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Ellendale
Location
Mcintosh County, North Dakota
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
IAP
Queue status
Withdrawn
Entered queue
9 November 2001

Location

Marker shows the centre of Mcintosh County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mcintosh County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem