United States › Grid › Interconnection queues › North Dakota
OTHER · MISOOther project G150, Mcintosh County
Other project G150, Mcintosh County is a 12.0 MW other request in interconnection study in the MISO interconnection queue, in Mcintosh County, North Dakota.
- PlanningQueued Nov 2001 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2002 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- G150
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Mcintosh County, North Dakota
- Technology
- Other: 12.0 MW
- Total requested
- 12.0 MW
- Queue status
- Active
- Entered queue
- 13 November 2001
- Proposed online date
- February 2002
Location
Marker shows the centre of Mcintosh County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Mcintosh County
- Onshore wind project J1040, Mcintosh CountyOnshore wind · 250 MW · under construction
- Coal project GI-0111, Mcintosh CountyCoal · 750 MW · withdrawn
- Onshore wind project GI-0114, Mcintosh CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GI-0115, Mcintosh CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2018-008, Mcintosh CountyOnshore wind · 252 MW · withdrawn
- Onshore wind project J209, Mcintosh CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project G988, Mcintosh CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G624, Mcintosh CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GI-0812, Mcintosh CountyOnshore wind · 150 MW · withdrawn
- Solar project J929, Mcintosh CountySolar · 25.0 MW · withdrawn
- Onshore wind project G283, Mcintosh CountyOnshore wind · 19.0 MW · withdrawn
- Onshore wind project G307, Mcintosh CountyOnshore wind · 19.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem