United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

SOLAR Β· MISO

Solar project J929, Mcintosh County

Solar project J929, Mcintosh County is a 25.0 MW solar request withdrawn in the MISO interconnection queue, in Mcintosh County, North Dakota, connecting to MONTANA-DAKOTA UTILITIES CO..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J929
Grid region
MISO (Midcontinent)
Utility / transmission owner
MONTANA-DAKOTA UTILITIES CO.
Connection point (POI)
Wishek 41.6 kV Substation
Location
Mcintosh County, North Dakota
Technology
Solar: 25.0 MW
Total requested
25.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
June 2021
Withdrawn
October 2019

Location

Marker shows the centre of Mcintosh County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mcintosh County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem