SOLAR · MISOSolar project J1034, Stoddard County
Solar project J1034, Stoddard County is a 225 MW solar request under construction in the MISO interconnection queue, in Stoddard County, Missouri, connecting to Ameren Missouri.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedOct 2021 (completed)
- Construction (current stage)
- OperatingTarget Jun 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1034
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Ameren Missouri
- Connection point (POI)
- Stoddard - Morley 161kV Line Tap
- Location
- Stoddard County, Missouri
- Technology
- Solar: 225 MW
- Total requested
- 225 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 12 October 2021
- Proposed online date
- June 2024
Location
Marker shows the centre of Stoddard County; the queue data does not give exact sites.
Other requests in Stoddard County
- Solar project J2524, Stoddard CountySolar · 200 MW · in study
- Solar project J3337, Stoddard CountySolar · 230 MW · withdrawn
- Battery storage project J3906, Stoddard CountyBattery storage · 140 MW · withdrawn
- Solar project J782, Stoddard CountySolar · 100 MW · withdrawn
- Battery storage project J1033, Stoddard CountyBattery storage · 50.0 MW · withdrawn
- Solar project J2387, Stoddard CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem