United States › Grid › Interconnection queues › Missouri
SOLAR · MISOSolar project J2524, Stoddard County
Solar project J2524, Stoddard County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Stoddard County, Missouri, connecting to AMEREN MISSOURI.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2524
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- 5STODDARD - 5MORLEY (AECI) 161kV
- Location
- Stoddard County, Missouri
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- November 2026
Location
Marker shows the centre of Stoddard County; the queue data does not give exact sites.
Other requests in Stoddard County
- Solar project J1034, Stoddard CountySolar · 225 MW · under construction
- Solar project J3337, Stoddard CountySolar · 230 MW · withdrawn
- Battery storage project J3906, Stoddard CountyBattery storage · 140 MW · withdrawn
- Solar project J782, Stoddard CountySolar · 100 MW · withdrawn
- Battery storage project J1033, Stoddard CountyBattery storage · 50.0 MW · withdrawn
- Solar project J2387, Stoddard CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem