🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1255, Ionia County

Solar project J1255, Ionia County is a 200 MW solar request under construction in the MISO interconnection queue, in Ionia County, Michigan, connecting to METC.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedOct 2022 (completed)
  3. Construction (current stage)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1255
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Marquette - Vergennes 138 kV Line Tap
Location
Ionia County, Michigan
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
31 October 2022
Proposed online date
October 2025

Location

Marker shows the centre of Ionia County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Ionia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem