Solar + storage project J2279, Ionia County

Solar + storage project J2279, Ionia County is a 150 MW solar + storage request withdrawn in the MISO interconnection queue, in Ionia County, Michigan, connecting to WOLVERINE POWER SUPPLY COOPERATIVE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2279
Grid region
MISO (Midcontinent)
Utility / transmission owner
WOLVERINE POWER SUPPLY COOPERATIVE
Connection point (POI)
Burnips to Tremaine 138 kV line
Location
Ionia County, Michigan
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
21 July 2021
Proposed online date
August 2025
Withdrawn
March 2025

Location

Marker shows the centre of Ionia County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Ionia County