United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR + STORAGE Β· MISOSolar + storage project J2279, Ionia County
Solar + storage project J2279, Ionia County is a 150 MW solar + storage request withdrawn in the MISO interconnection queue, in Ionia County, Michigan, connecting to WOLVERINE POWER SUPPLY COOPERATIVE.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2021 (completed)
- Withdrawn / abandonedMar 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2279
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- WOLVERINE POWER SUPPLY COOPERATIVE
- Connection point (POI)
- Burnips to Tremaine 138 kV line
- Location
- Ionia County, Michigan
- Technology
- Solar: 150 MW Β· Battery
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 21 July 2021
- Proposed online date
- August 2025
- Withdrawn
- March 2025
Location
Marker shows the centre of Ionia County; the queue data does not give exact sites.
Other requests in Ionia County
- Solar project J1255, Ionia CountySolar Β· 200 MW Β· under construction
- Onshore wind project J1292, Ionia CountyOnshore wind Β· 198 MW Β· agreement signed
- Solar project J3545, Ionia CountySolar Β· 200 MW Β· in study
- Onshore wind project J4055, Ionia CountyOnshore wind Β· 198 MW Β· in study
- Solar project J1403, Ionia CountySolar Β· 200 MW Β· withdrawn
- Solar project J2774, Ionia CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project J1064, Ionia CountyOnshore wind Β· 200 MW Β· withdrawn
- Battery storage project J3220, Ionia CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project J1554, Ionia CountySolar Β· 150 MW Β· withdrawn
- Onshore wind project J921, Ionia CountyOnshore wind Β· 147 MW Β· withdrawn
- Solar project J2725, Ionia CountySolar Β· 100 MW Β· withdrawn
- Other project G216 CONS 90, Ionia CountyOther Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem