πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

BATTERY STORAGE Β· MISO

Battery storage project J3220, Ionia County

Battery storage project J3220, Ionia County is a 200 MW battery storage request withdrawn in the MISO interconnection queue, in Ionia County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2024 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3220
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Peddler
Location
Ionia County, Michigan
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
5 August 2024
Proposed online date
October 2026
Withdrawn
August 2025

Location

Marker shows the centre of Ionia County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Ionia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem