ONSHORE WIND Β· MISO

Onshore wind project J1064, Ionia County

Onshore wind project J1064, Ionia County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Ionia County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedNov 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1064
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Marquette - Vergennes 138 kV Line Tap
Location
Ionia County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
October 2020
Withdrawn
November 2019

Location

Marker shows the centre of Ionia County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan