SOLAR · MISOSolar project J1421, East Feliciana Parish County
Solar project J1421, East Feliciana Parish County is a 300 MW solar request under construction in the MISO interconnection queue, in East Feliciana Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusUnder construction
- PlanningQueued Apr 2019 (completed)
- ConsentedOct 2024 (completed)
- Construction (current stage)
- OperatingTarget Dec 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1421
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Moler 230 kV Substation
- Location
- East Feliciana Parish County, Louisiana
- Technology
- Solar: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 28 October 2024
- Proposed online date
- December 2024
Location
Marker shows the centre of East Feliciana Parish County; the queue data does not give exact sites.
Other requests in East Feliciana Parish County
- Solar project J3128, East Feliciana Parish CountySolar · 100 MW · in study
- Solar + storage project J3630, East Feliciana Parish CountySolar + storage · 77.0 MW · in study
- Solar project J1029, East Feliciana Parish CountySolar · 200 MW · withdrawn
- Solar + storage project J3019, East Feliciana Parish CountySolar + storage · 180 MW · withdrawn
- Solar project J553, East Feliciana Parish CountySolar · 50.0 MW · withdrawn
- Battery storage project J3129, East Feliciana Parish CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem