United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J1007, Crittenden County
Solar project J1007, Crittenden County is a 200 MW solar request under construction in the MISO interconnection queue, in Crittenden County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedAug 2020 (completed)
- Construction (current stage)
- OperatingDec 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1007
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- Marion - Marked Tree 161kV Line Tap
- Location
- Crittenden County, Arkansas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 12 August 2020
- Proposed online date
- June 2023
- Came online
- December 2023
Location
Marker shows the centre of Crittenden County; the queue data does not give exact sites.
Other requests in Crittenden County
- Solar project J934, Crittenden CountySolar · 200 MW · under construction
- Solar project J2477, Crittenden CountySolar · 600 MW · in study
- Solar project J2482, Crittenden CountySolar · 300 MW · in study
- Solar project J4074, Crittenden CountySolar · 300 MW · in study
- Solar + storage project J4012, Crittenden CountySolar + storage · 300 MW · in study
- Wind + storage project J3230, Crittenden CountyWind + storage · 200 MW · in study
- Solar project J3090, Crittenden CountySolar · 200 MW · in study
- Wind + storage project J3122, Crittenden CountyWind + storage · 200 MW · in study
- Surplus; J1007Battery storage · 180 MW · in study
- Solar + storage project J2734, Crittenden CountySolar + storage · 150 MW · in study
- Solar project J2090, Crittenden CountySolar · 300 MW · withdrawn
- Solar project J2028, Crittenden CountySolar · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem