United States › Grid › Interconnection queues › Arkansas
BATTERY STORAGE · MISOSurplus; J1007
Surplus; J1007 is a 180 MW battery storage request in interconnection study in the MISO interconnection queue, in Crittenden County, Arkansas, connecting to ENTERGY LOUISIANA.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S1094
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- BOB WHITE
- Location
- Crittenden County, Arkansas
- Technology
- Battery: 180 MW
- Total requested
- 180 MW
- Queue status
- Active
- Entered queue
- 8 April 2025
- Proposed online date
- October 2026
Location
Marker shows the centre of Crittenden County; the queue data does not give exact sites.
Other requests in Crittenden County
- Solar project J1007, Crittenden CountySolar · 200 MW · under construction
- Solar project J934, Crittenden CountySolar · 200 MW · under construction
- Solar project J2477, Crittenden CountySolar · 600 MW · in study
- Solar project J2482, Crittenden CountySolar · 300 MW · in study
- Solar project J4074, Crittenden CountySolar · 300 MW · in study
- Solar + storage project J4012, Crittenden CountySolar + storage · 300 MW · in study
- Wind + storage project J3230, Crittenden CountyWind + storage · 200 MW · in study
- Solar project J3090, Crittenden CountySolar · 200 MW · in study
- Wind + storage project J3122, Crittenden CountyWind + storage · 200 MW · in study
- Solar + storage project J2734, Crittenden CountySolar + storage · 150 MW · in study
- Solar project J2090, Crittenden CountySolar · 300 MW · withdrawn
- Solar project J2028, Crittenden CountySolar · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem