ONSHORE WIND · MISO

Onshore wind project J1437, Carroll County

Onshore wind project J1437, Carroll County is a 180 MW onshore wind request under construction in the MISO interconnection queue, in Carroll County, Arkansas, connecting to ARKANSAS ELECTRIC COOPERATIVE CORPORATION.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedDec 2021 (completed)
  3. Construction (current stage)
  4. OperatingTarget May 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1437
Grid region
MISO (Midcontinent)
Utility / transmission owner
ARKANSAS ELECTRIC COOPERATIVE CORPORATION
Connection point (POI)
AECC Dry Creek 161kV Switchyard Station
Location
Carroll County, Arkansas
Technology
Wind: 180 MW
Total requested
180 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
22 December 2021
Proposed online date
May 2024

Location

Marker shows the centre of Carroll County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Carroll County