ONSHORE WIND Β· MISO

Onshore wind project J899, Carroll County

Onshore wind project J899, Carroll County is a 180 MW onshore wind request withdrawn in the MISO interconnection queue, in Carroll County, Arkansas, connecting to Entergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J899
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Green Forest South - Harrison West 161kV
Location
Carroll County, Arkansas
Technology
Wind: 180 MW
Total requested
180 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
October 2019
Withdrawn
March 2019

Location

Marker shows the centre of Carroll County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Carroll County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem