United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project J984, Gratiot County

Onshore wind project J984, Gratiot County is a 200 MW onshore wind request under construction in the MISO interconnection queue, in Gratiot County, Michigan, connecting to METC.

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedMay 2021 (completed)
  3. Construction (current stage)
  4. OperatingDec 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J984
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Nelson Road – Murphy 345kV line
Location
Gratiot County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
12 March 2018
Agreement signed
7 May 2021
Proposed online date
October 2022
Came online
December 2023

Location

Marker shows the centre of Gratiot County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Gratiot County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem