Onshore wind project G934, Gratiot County

Onshore wind project G934, Gratiot County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Gratiot County, Michigan.

Queue statusOperating
  1. PlanningQueued Jan 2012 (completed)
  2. ConsentedJul 2017 (completed)
  3. Construction (completed)
  4. OperatingDec 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G934
Grid region
MISO (Midcontinent)
Connection point (POI)
METC Nelson Road 345kV substation
Location
Gratiot County, Michigan
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
24 January 2012
Agreement signed
24 July 2017
Proposed online date
December 2020
Came online
December 2020

Location

Marker shows the centre of Gratiot County; the queue data does not give exact sites.