ONSHORE WIND · MISO

Onshore wind project J3909, Gratiot County

Onshore wind project J3909, Gratiot County is a 175 MW onshore wind request in interconnection study in the MISO interconnection queue, in Gratiot County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3909
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
ALMA - VESTABURG 138.0kV
Location
Gratiot County, Michigan
Technology
Wind: 175 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
28 February 2025
Proposed online date
May 2030

Location

Marker shows the centre of Gratiot County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Gratiot County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem