United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J1458, Washington County
Solar project J1458, Washington County is a 200 MW solar request under construction in the MISO interconnection queue, in Washington County, Mississippi, connecting to ENTERGY MISSISSIPPI.
Queue statusUnder construction
- PlanningQueued Apr 2019 (completed)
- ConsentedJan 2022 (completed)
- Construction (current stage)
- OperatingTarget Dec 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1458
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY MISSISSIPPI
- Connection point (POI)
- Ray Braswell - Tinnin - Gerald Andrus 230kV Line
- Location
- Washington County, Mississippi
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 25 January 2022
- Proposed online date
- December 2024
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Washington County
- Solar project J4121, Washington CountySolar · 300 MW · in study
- Battery storage project S1127, Washington CountyBattery storage · 170 MW · in study
- Solar project J2175, Washington CountySolar · 350 MW · withdrawn
- Solar project J3375, Washington CountySolar · 200 MW · withdrawn
- Solar project J3126, Washington CountySolar · 200 MW · withdrawn
- Solar project J945, Washington CountySolar · 200 MW · withdrawn
- Solar + storage project J3748, Washington CountySolar + storage · 200 MW · withdrawn
- Solar + storage project J2905, Washington CountySolar + storage · 100 MW · withdrawn
- Solar project J1070, Washington CountySolar · 100 MW · withdrawn
- Solar project J3657, Washington CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem