Solar project J3657, Washington County

Solar project J3657, Washington County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Washington County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3657
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
Greer Solar substation J1458
Location
Washington County, Mississippi
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
4 April 2024
Proposed online date
June 2028
Withdrawn
October 2025

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.