πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

SOLAR Β· MISO

Solar project J945, Washington County

Solar project J945, Washington County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Washington County, Mississippi, connecting to Entergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J945
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Gerald Andrus - Clinton Industrial 230 kV Line
Location
Washington County, Mississippi
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
September 2019
Withdrawn
January 2019

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem