SOLAR Β· MISOSolar project J3375, Washington County
Solar project J3375, Washington County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Washington County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedSep 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3375
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY MISSISSIPPI, LLC.
- Connection point (POI)
- Gerald Andrus 230 kV Substation
- Location
- Washington County, Mississippi
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 17 April 2024
- Proposed online date
- March 2028
- Withdrawn
- September 2025
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Washington County
- Solar project J1458, Washington CountySolar Β· 200 MW Β· under construction
- Solar project J4121, Washington CountySolar Β· 300 MW Β· in study
- Battery storage project S1127, Washington CountyBattery storage Β· 170 MW Β· in study
- Solar project J2175, Washington CountySolar Β· 350 MW Β· withdrawn
- Solar project J3126, Washington CountySolar Β· 200 MW Β· withdrawn
- Solar project J945, Washington CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project J3748, Washington CountySolar + storage Β· 200 MW Β· withdrawn
- Solar + storage project J2905, Washington CountySolar + storage Β· 100 MW Β· withdrawn
- Solar project J1070, Washington CountySolar Β· 100 MW Β· withdrawn
- Solar project J3657, Washington CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem