United States › Grid › Interconnection queues › Illinois

SOLAR · MISO

Solar project J800, White County

Solar project J800, White County is a 250 MW solar request under construction in the MISO interconnection queue, in White County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusUnder construction
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedApr 2020 (completed)
  3. Construction (current stage)
  4. OperatingDec 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J800
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Crossville West Substation 138kV Bus - Albion South - Norris City 138 kV Line
Location
White County, Illinois
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
16 June 2017
Agreement signed
22 April 2020
Proposed online date
October 2022
Came online
December 2024

Location

Marker shows the centre of White County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in White County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem