United States › Grid › Interconnection queues › Michigan
SOLAR · MISOSolar project J1224, Washtenaw County
Solar project J1224, Washtenaw County is a 170 MW solar request under construction in the MISO interconnection queue, in Washtenaw County, Michigan, connecting to ITC MIDWEST.
Queue statusUnder construction
- PlanningQueued Apr 2019 (completed)
- ConsentedMar 2023 (completed)
- Construction (current stage)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1224
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Majestic - Milan 345 kV Line Tap
- Location
- Washtenaw County, Michigan
- Technology
- Solar: 170 MW
- Total requested
- 170 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 27 April 2019
- Agreement signed
- 2 March 2023
- Proposed online date
- October 2025
Location
Marker shows the centre of Washtenaw County; the queue data does not give exact sites.
Other requests in Washtenaw County
- Solar project J799, Washtenaw CountySolar · 189 MW · under construction
- Battery storage project J1659, Washtenaw CountyBattery storage · 100 MW · under construction
- Battery storage project J1329, Washtenaw CountyBattery storage · 20.0 MW · under construction
- Solar project J1062, Washtenaw CountySolar · 200 MW · agreement signed
- Gas project J3923, Washtenaw CountyGas · 1,414 MW · in study
- Solar project J3945, Washtenaw CountySolar · 245 MW · in study
- Surplus; J1062Other · 150 MW · in study
- Battery storage project J3009, Washtenaw CountyBattery storage · 150 MW · in study
- Battery storage project J3654, Washtenaw CountyBattery storage · 150 MW · in study
- Battery storage project J1844, Washtenaw CountyBattery storage · 100 MW · in study
- Surplus; J1224/J1329Other · 85.1 MW · in study
- Solar project J3653, Washtenaw CountySolar · 80.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem