Solar project J3653, Washtenaw County

Solar project J3653, Washtenaw County is a 80.0 MW solar request in interconnection study in the MISO interconnection queue, in Washtenaw County, Michigan, connecting to ITC.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3653
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
Line tap on Superior-Wayne 120kV line at 42.275480, -83.628250
Location
Washtenaw County, Michigan
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
5 April 2024
Proposed online date
June 2028

Location

Marker shows the centre of Washtenaw County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Washtenaw County