United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J1424, Beauregard Parish County

Solar project J1424, Beauregard Parish County is a 200 MW solar request under construction in the MISO interconnection queue, in Beauregard Parish County, Louisiana, connecting to CLECO POWER.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedNov 2021 (completed)
  3. Construction (current stage)
  4. OperatingTarget Sep 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1424
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Cooper - Penton Road 230kV Line
Location
Beauregard Parish County, Louisiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
29 November 2021
Proposed online date
September 2024

Location

Marker shows the centre of Beauregard Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Beauregard Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem