SOLAR Β· MISO

Solar project J2310, Beauregard Parish County

Solar project J2310, Beauregard Parish County is a 300 MW solar request withdrawn in the MISO interconnection queue, in Beauregard Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2310
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Rhodes
Location
Beauregard Parish County, Louisiana
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
9 September 2021
Proposed online date
April 2024
Withdrawn
October 2023

Location

Marker shows the centre of Beauregard Parish County; the queue data does not give exact sites.