United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J4092, Beauregard Parish County
Solar project J4092, Beauregard Parish County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Beauregard Parish County, Louisiana, connecting to CLECO POWER.
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4092
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Deridder - Longville 138.0kV
- Location
- Beauregard Parish County, Louisiana
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 October 2025
- Proposed online date
- January 2030
Location
Marker shows the centre of Beauregard Parish County; the queue data does not give exact sites.
Other requests in Beauregard Parish County
- Solar project J1424, Beauregard Parish CountySolar · 200 MW · under construction
- Solar project J3939, Beauregard Parish CountySolar · 386 MW · in study
- Solar + storage project J4201, Beauregard Parish CountySolar + storage · 250 MW · in study
- Battery storage project S1123, Beauregard Parish CountyBattery storage · 200 MW · in study
- Solar project J4188, Beauregard Parish CountySolar · 140 MW · in study
- Solar + storage project J2911, Beauregard Parish CountySolar + storage · 810 MW · withdrawn
- Solar + storage project J2882, Beauregard Parish CountySolar + storage · 410 MW · withdrawn
- Solar project J2310, Beauregard Parish CountySolar · 300 MW · withdrawn
- Solar + storage project J2884, Beauregard Parish CountySolar + storage · 276 MW · withdrawn
- Solar + storage project J2020, Beauregard Parish CountySolar + storage · 260 MW · withdrawn
- Solar project J2505, Beauregard Parish CountySolar · 250 MW · withdrawn
- Solar project J2441, Beauregard Parish CountySolar · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem