United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J919, Jackson County
Solar project J919, Jackson County is a 180 MW solar request under construction in the MISO interconnection queue, in Jackson County, Arkansas, connecting to Entergy.
Queue statusUnder construction
- PlanningQueued Jun 2017 (completed)
- ConsentedNov 2019 (completed)
- Construction (current stage)
- OperatingOct 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J919
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- Cash - Newport AB 161 kV Line Tap
- Location
- Jackson County, Arkansas
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 16 June 2017
- Agreement signed
- 21 November 2019
- Proposed online date
- February 2022
- Came online
- October 2023
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- Solar project J2261, Jackson CountySolar · 625 MW · in study
- Solar project J2262, Jackson CountySolar · 625 MW · in study
- Solar project J3192, Jackson CountySolar · 500 MW · in study
- Solar project J1855, Jackson CountySolar · 500 MW · in study
- Solar project J2252, Jackson CountySolar · 300 MW · in study
- Onshore wind project J2613, Jackson CountyOnshore wind · 300 MW · in study
- Onshore wind project J2641, Jackson CountyOnshore wind · 200 MW · in study
- Solar + storage project J3120, Jackson CountySolar + storage · 200 MW · in study
- Solar + storage project GEN-2024-114, Jackson CountySolar + storage · 199 MW · in study
- Solar project J1856, Jackson CountySolar · 150 MW · in study
- Solar project J2682, Jackson CountySolar · 500 MW · withdrawn
- Solar project J2936, Jackson CountySolar · 500 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem