🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arkansas

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-114, Jackson County

Solar + storage project GEN-2024-114, Jackson County is a 199 MW solar + storage request in interconnection study in the SPP interconnection queue, in Jackson County, Arkansas, connecting to SWPA.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-114
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SWPA
Connection point (POI)
Jonesboro - Independence County 161 kV Line
Location
Jackson County, Arkansas
Technology
Solar: 199 MW · Battery
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
December 2028

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem