United States › Grid › Interconnection queues › Missouri

SOLAR · MISO

Solar project J976, Warren County

Solar project J976, Warren County is a 300 MW solar request under construction in the MISO interconnection queue, in Warren County, Missouri, connecting to Ameren Missouri.

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedOct 2021 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jun 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J976
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Montgomery - Enon 345kV Line Tap
Location
Warren County, Missouri
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
12 March 2018
Agreement signed
12 October 2021
Proposed online date
June 2024

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem