BATTERY STORAGE Β· MISO

Battery storage project J1039, Warren County

Battery storage project J1039, Warren County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Warren County, Missouri, connecting to Ameren Missouri.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1039
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Enon - Montogomery 345kV Line Tap
Location
Warren County, Missouri
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
October 2021
Withdrawn
March 2021

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Warren County