United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in ERCOT (Texas) — page 6
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Welder Solar II Solar · Welder Solar, LLC |
300 MW | Withdrawn / abandoned |
| Caprock Wind Onshore wind · Eurus |
300 MW | Withdrawn / abandoned |
| Sitges Wind 2 Onshore wind · NextEra Energy Interconnection Holdings, LLC |
300 MW | Withdrawn / abandoned |
| Bird Dog Wind Onshore wind · Americlean |
300 MW | Withdrawn / abandoned |
| Pullman Road Wind Onshore wind · SunEdison |
300 MW | Withdrawn / abandoned |
| CullenAlta Gas · ALTA POWER LLC |
300 MW | Withdrawn / abandoned |
| Sibyl Power Station Gas · WattBridge Energy, LLC |
299 MW | Withdrawn / abandoned |
| Coati Solar Solar · Coati Solar, LLC |
296 MW | Withdrawn / abandoned |
| Lamar Power Project Expansion Gas · FPL Energy, LLC |
296 MW | Withdrawn / abandoned |
| Wise Peakers Gas · Suez Energy, NA |
291 MW | Withdrawn / abandoned |
| Denver Unit Cogen Plant Gas · Occidental Energy Ventures Corp |
291 MW | Withdrawn / abandoned |
| 2W Whatley Phase 2 Onshore wind · TripleT Renewable Enrgy Solutions, LLC |
290 MW | Withdrawn / abandoned |
| Lon C. Hill Power Station Gas · NuCoastal Power Corporation |
289 MW | Withdrawn / abandoned |
| Changing Winds Onshore wind · TriGlobal |
288 MW | Withdrawn / abandoned |
| Pumpkin Farm Wind Onshore wind · Apex Clean |
281 MW | Withdrawn / abandoned |
| Last Stop Solar Solar · OE Renewables |
280 MW | Withdrawn / abandoned |
| Double R Solar Solar · Double R Solar Farm |
280 MW | Withdrawn / abandoned |
| Matagorda Energy Center Battery storage · Apex Compressed Air Energy Storage |
280 MW | Withdrawn / abandoned |
| Pecan Creek 1 Gas Gas · NTE Energy |
280 MW | Withdrawn / abandoned |
| Johnson County 2 Gas · Brazos Electric Cooperative |
275 MW | Withdrawn / abandoned |
| Quail Run Phase III Gas · Navasota Energy Partners, LP |
275 MW | Withdrawn / abandoned |
| Colorado Bend Phase 3 Gas · Navasota Wharton Energy Partners |
275 MW | Withdrawn / abandoned |
| Colorado Bend Phase 3 Gas · Navasota Wharton Energy Partners |
275 MW | Withdrawn / abandoned |
| Greenwolfe Solar Alt POI Solar · EDF Renewables Development, Inc. |
274 MW | Withdrawn / abandoned |
| Whitethorn Solar Solar · Greasewood III LLC |
274 MW | Withdrawn / abandoned |
| Sentinel Solar Solar · Alamo Ranch Solar Project, LLC |
271 MW | Withdrawn / abandoned |
| cancelled Chamisa CAES Battery storage · Chamisa |
270 MW | Withdrawn / abandoned |
| Crows Nest Windfarm Onshore wind · FPL Energy, LLC |
270 MW | Withdrawn / abandoned |
| Apis Storage Battery storage · S&S Renewables LLC |
268 MW | Withdrawn / abandoned |
| OCI SunRoper ESS Other · OCI SunRoper LLC |
266 MW | Withdrawn / abandoned |
| Spitfire Wind ph 1 Onshore wind · Clipper Windpower |
265 MW | Withdrawn / abandoned |
| Randado Wind Farm Onshore wind · American Shoreline, Inc |
264 MW | Withdrawn / abandoned |
| Emerald Hill Energy Storage Battery storage · Emerald Hill Energy Storage LLC |
261 MW | Withdrawn / abandoned |
| BRP Denali BESS Battery storage · BRP Denali BESS LLC |
258 MW | Withdrawn / abandoned |
| Firefox BESS Battery storage · Horizon Energy Storage Greenfield Project Holdings LLC |
258 MW | Withdrawn / abandoned |
| El Zorro Solar Solar · Cypress Creek Renewables |
253 MW | Withdrawn / abandoned |
| Redonda Solar Solar · J&R Power DevCo, LLC |
253 MW | Withdrawn / abandoned |
| Neal Solar Solar · SolarGen Resources LLC |
252 MW | Withdrawn / abandoned |
| BRP Batura BESS Battery storage · BRP Batura BESS LLC |
252 MW | Withdrawn / abandoned |
| Slama Solar Solar · Burkburnett Solar, LLC |
252 MW | Withdrawn / abandoned |
| Hat Creek Solar Solar · Hat Creek Solar, LLC |
252 MW | Withdrawn / abandoned |
| Boxcar Solar 2 Solar · EDF Renewables Development, Inc. |
251 MW | Withdrawn / abandoned |
| Horse Wrangler Solar Solar · Horse Wrangler Solar Project, LLC |
251 MW | Withdrawn / abandoned |
| Lenorah Project Onshore wind · Wind Tex Energy, LLC |
251 MW | Withdrawn / abandoned |
| Deaf Smith Wind Project Onshore wind · Third Planet Windpower LLC |
251 MW | Withdrawn / abandoned |
| Zapata Windfarm Onshore wind · Eon Climate & Renewables |
251 MW | Withdrawn / abandoned |
| Blanco Canyon Wind Onshore wind · Invenergy |
251 MW | Withdrawn / abandoned |
| Bottom Grass Solar MW Increase Solar · Bottom Grass Solar Project, LLC |
250 MW | Withdrawn / abandoned |
| County Line Solar Solar · S Power |
250 MW | Withdrawn / abandoned |
| Briggs Storage II Battery storage · Briggs Solar, LLC |
250 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)