Last Stop Solar

Last Stop Solar is a 280 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
16INR0094
Grid region
ERCOT (Texas)
Developer
OE Renewables
Connection point (POI)
Screwbean (#1095)
Technology
Solar: 280 MW
Total requested
280 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
10 March 2015
Proposed online date
October 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in