United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTLenorah Project
Lenorah Project is a 251 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2007 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedFeb 2009 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 08INR0040
- Grid region
- ERCOT (Texas)
- Developer
- Wind Tex Energy, LLC
- Technology
- Wind: 251 MW
- Total requested
- 251 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 19 January 2007
- Agreement signed
- 2 February 2009
- Proposed online date
- December 2050
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem