BATTERY STORAGE · ERCOT

Briggs Storage II

Briggs Storage II is a 250 MW battery storage request withdrawn in the ERCOT interconnection queue, in Haskell County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2025 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0482
Grid region
ERCOT (Texas)
Developer
Briggs Solar, LLC
Connection point (POI)
345kV Kilby Station (60089)
Location
Haskell County, Texas
Technology
Battery: 250 MW
Total requested
250 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Entered queue
18 June 2025
Proposed online date
December 2027
Withdrawn
July 2025

Location

Marker shows the centre of Haskell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Haskell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem