United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTBriggs Storage II
Briggs Storage II is a 250 MW battery storage request withdrawn in the ERCOT interconnection queue, in Haskell County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2025 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 27INR0482
- Grid region
- ERCOT (Texas)
- Developer
- Briggs Solar, LLC
- Connection point (POI)
- 345kV Kilby Station (60089)
- Location
- Haskell County, Texas
- Technology
- Battery: 250 MW
- Total requested
- 250 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Entered queue
- 18 June 2025
- Proposed online date
- December 2027
- Withdrawn
- July 2025
Location
Marker shows the centre of Haskell County; the queue data does not give exact sites.
Other requests in Haskell County
- Briggs StorageSolar + storage · 336 MW · agreement signed
- Briggs SolarSolar + storage · 324 MW · agreement signed
- Quantum StorageSolar + storage · 322 MW · agreement signed
- Solace StorageSolar + storage · 322 MW · agreement signed
- Quantum SolarSolar + storage · 322 MW · agreement signed
- Solace SolarSolar + storage · 322 MW · agreement signed
- Rubicon Alpha WindOnshore wind · 226 MW · agreement signed
- Inertia SolarSolar · 202 MW · agreement signed
- Millers Branch Solar ISolar · 200 MW · agreement signed
- Millers Branch Solar IISolar · 178 MW · agreement signed
- Millers Branch Solar IIISolar · 133 MW · agreement signed
- Grasshopper SolarSolar · 408 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem