SOLAR Β· ERCOT

County Line Solar

County Line Solar is a 250 MW solar request withdrawn in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2017 (completed)
  2. Withdrawn / abandonedJan 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0113
Grid region
ERCOT (Texas)
Developer
S Power
Connection point (POI)
60385 Solstice 138kV
Location
Pecos County, Texas
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
14 August 2017
Proposed online date
December 2022
Withdrawn
January 2021

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem