GAS Β· ERCOT

Colorado Bend Phase 3

Colorado Bend Phase 3 is a 275 MW gas request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
11INR0049
Grid region
ERCOT (Texas)
Developer
Navasota Wharton Energy Partners
Technology
Gas: 275 MW
Total requested
275 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
19 November 2008
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem